The PBS Changes Register shows all changes made to the job's Price Breakdown Structure (PBS). You also have the option to copy the PBS changes log when you create a new job from an existing job. After you select activate the PBS changes log, an entry will be made in the PBS Changes Register for each action taken that affects the job's cost or target price.
The PBS Changes Register shows the changes made to the job folder and automatically calculates (and records) their impact on the job’s cost and target price.
When used in conjunction with the Change Management module, the PBS Changes Register constantly monitors the job folder for any changes that affect the job’s cost or target price, such as new or deleted items of work, changes to production rates, changes to quantities, and more.
When you activate the PBS Changes Register you can:
If you want to clear the changes log, such as when you create a new job from an existing job, and inadvertently copy the previous PBS changes log, you can use the Clear Changes Log option to remove existing changes. You can also clear the PBS changes log at your discretion.
You can control who can clear the log by assigning permissions in the Access Control Register.
The PBS changes log cannot be restored after it is cleared.
Additional Information